Party Wall Section 6

|

If you are planning foundations, drainage, piling, underpinning-related works or a basement near a neighbouring property, Party Wall Section 6 is often one of the most important parts of the Act to check early. In simple terms, it deals with excavation and construction close to adjoining buildings, and it may require formal notice before work begins. This guide explains the 3 metre rule, the 6 metre rule, when a Section 6 notice is usually needed, and what happens if a neighbour dissents or does not reply.

Party Wall Section 6 explained for excavation near neighbouring foundations in London

3 Metre Rule

May apply where excavation is within 3 metres of a neighbouring building or structure and goes deeper than the bottom of the adjoining foundations.

6 Metre Rule

May apply where excavation is within 6 metres and falls within the 45 degree line taken from the bottom of the adjoining foundations.

Notice Period

A Section 6 notice is generally served at least one month before the planned excavation start date.

Response Window

The adjoining owner usually has 14 days to consent. No reply or dissent normally means a dispute has arisen.

What is Party Wall Section 6?

Section 6 of the Party Wall etc. Act 1996 covers excavation and construction close to neighbouring buildings or structures in England and Wales. It is commonly relevant where a building owner proposes new foundations for a rear extension, side return extension, basement excavation, retaining structure, drainage trench, or other structural work close to an adjoining owner’s property.

It is important not to confuse the Party Wall Act with planning permission or Building Regulations approval. These are separate regimes. Even where a scheme has planning consent and building control approval, the Act may still require notice to be served and the statutory procedure to be followed. For a broader overview, see our guide on what the Party Wall Act is.

The 3 metre rule explained

The first and more familiar Section 6 trigger is the 3 metre rule. In general terms, Section 6 may apply where you propose to excavate within 3 metres of any part of a neighbouring building or structure and any part of your excavation will go below the bottom of the adjoining foundations.

This often affects standard London residential projects, particularly rear extensions and side return works where new trench-fill foundations are being dug close to a shared boundary. It can also arise with deep drainage runs, retaining walls and similar works depending on the depth and position of the excavation.

The 6 metre rule and the 45 degree test

Section 6 can also apply even where the excavation is more than 3 metres away. This second test is commonly referred to as the 6 metre rule. It may apply where excavation is within 6 metres of a neighbouring building or structure and the proposed excavation falls within a line drawn downwards at 45 degrees from the bottom of the adjoining owner’s foundations.

In practice, this second test is often relevant for deeper foundations, piled schemes and basement works. It is usually not something that should be guessed at on site. It is better reviewed against proper drawings and sections so the position is clear before works start.

If your project involves deeper excavation near an adjoining property, our Party Wall Survey for Excavations in London service can help determine whether the Section 6 procedure is likely to apply.

Section 6 Trigger Comparison Table

Test Distance Depth / Geometry Typical Projects Usual Next Step
3 metre rule Within 3 metres of a neighbouring building or structure Excavation goes below the bottom of the adjoining foundations Rear extensions, side returns, drainage trenches, retaining walls Review drawings, confirm likely foundation relationship, and serve notice if the test is met
6 metre rule Within 6 metres of a neighbouring building or structure Excavation falls within the 45° line from the bottom of the adjoining foundations Basements, piled foundations, deeper structural schemes Carry out a measured assessment using plans and sections, then serve notice if the test is met

When do you usually need to serve a Section 6 notice?

If either Section 6 test applies, the building owner will usually need to serve a formal notice at least one month before the planned starting date for the relevant excavation. A compliant notice should not be left until the last minute. In practice, it is usually best to review the architectural and structural drawings early, identify the correct adjoining owners, and serve notice with enough time to avoid delay.

If you need support with drafting and serving notices properly, see our Party Wall Notices in London service.

What should a Party Wall Section 6 notice include?

A Section 6 notice should clearly describe the proposed excavation and construction works, identify the site address, and include the intended start date. It should also be accompanied by sufficient plans and sections showing the location and depth of the proposed excavation and, where relevant, the position of any new building or structure.

Unclear notices are one of the most common causes of delay. Where drawings are vague or the depth information is incomplete, adjoining owners are more likely to have concerns and surveyor appointment can become slower than it needs to be.

What happens after the notice is served?

Once the notice has been served, the adjoining owner can consent, dissent, or fail to reply. If the adjoining owner gives written consent, the project can usually proceed in accordance with the Act and any agreed terms. If they dissent, or do not respond within 14 days, a dispute is usually deemed to have arisen under the Act.

At that stage, surveyor appointment is normally required. The parties may agree to use one surveyor, known as an agreed surveyor, or they may each appoint their own surveyor. You can read more about the agreed surveyor role, the building owner’s responsibilities, and guidance for the adjoining owner.

What is a Party Wall Award in a Section 6 matter?

Where a dispute has arisen, the surveyor or surveyors usually resolve the matter by preparing a Party Wall Award. The Award commonly deals with the timing and manner of the works, access arrangements, protective measures, and the rights and obligations of the parties under the Act.

If you would like more detail on that stage of the process, visit our Party Wall Awards page.

Common projects where Section 6 may apply

Section 6 often needs to be considered for residential and mixed-use projects across London, particularly where excavation is close to existing neighbouring structures. Typical examples include:

  • single-storey rear extensions with new foundations close to the boundary;
  • side return extensions in terraced or semi-detached properties;
  • basement excavations, retaining walls and underpinning-related works;
  • piled foundations and deeper structural schemes;
  • deep drainage runs or associated excavation near adjoining buildings.

Common Project Types and Whether Section 6 May Apply

Project Type Likelihood of Section 6 Being Relevant Comment
Single-storey rear extension near the boundary Often relevant Commonly arises where the new foundations are close to the neighbour and deeper than their existing foundations.
Side return extension in a terrace Often relevant Especially common in London where adjoining foundations may be shallow and close to the proposed excavation line.
Basement excavation Very often relevant Usually requires careful review of both the 3 metre and 6 metre tests.
Deep drainage run near adjoining property May be relevant Depends on route, depth, and relationship to neighbouring foundations.
Piled foundation scheme May be relevant Often needs a site-specific assessment because geometry and depth are critical.
Internal refurbishment with no qualifying excavation Usually not under Section 6 Other parts of the Act may still need to be reviewed depending on the proposed works.

Section 6 and basement works

Basement schemes are one of the clearest examples of why Section 6 should be reviewed early. They often involve deeper excavation, more complex structural sequencing, and a higher level of neighbour concern. In many cases, both the notice procedure and a detailed schedule of condition are sensible parts of the process.

For project-specific support, see our Party Wall Survey for Basement Works service and our Schedule of Condition Surveys page.

Why early advice matters

Section 6 issues are often less about the wording of the Act and more about timing, coordination and communication. A compliant notice served too late can affect the programme. Incomplete information can increase neighbour concern. Starting qualifying works without following the correct process can create avoidable dispute and delay.

Early review by an experienced surveyor can help identify whether the Act is likely to apply, confirm which neighbouring owners should be notified, and keep the process professional and neighbourly.

Section 6 Timeline at a Glance

Stage What Usually Happens Typical Timing
1. Review the drawings Check whether the 3 metre rule or the 6 metre / 45° test is likely to apply. Before notices are drafted
2. Serve notice Issue the Section 6 notice with plans and sections showing the proposed excavation and depth. At least 1 month before the planned start date
3. Await response The adjoining owner can consent, dissent, or fail to reply. 14 days from service
4. If consent is given Works may usually proceed in line with the Act and any agreed arrangements. After the notice period or as agreed
5. If dissent or no reply A dispute is deemed to have arisen and surveyor appointment is normally required. After the 14 day response period
6. Award stage The surveyor or surveyors prepare a Party Wall Award dealing with the timing and manner of the works. Before relevant works proceed where a dispute exists

Frequently Asked Questions

Section 6 is the part of the Party Wall etc. Act 1996 that deals with excavation and construction close to neighbouring buildings or structures. It is commonly relevant to foundations, basements, drainage runs and deeper excavation works near adjoining property.
The 3 metre rule may apply where you plan to excavate within 3 metres of a neighbouring building or structure and your excavation will go below the bottom of the adjoining foundations.
The 6 metre rule may apply where excavation is within 6 metres of a neighbouring building or structure and the proposed excavation falls within the 45 degree line taken from the bottom of the adjoining foundations.
A Section 6 notice is generally served at least one month before the planned start date for the relevant excavation. If work does not begin within 12 months of service, a fresh notice is often required.
If the adjoining owner does not consent within 14 days, the matter is usually treated as a dispute under the Act. A surveyor or surveyors would then normally need to be appointed so that an Award can be prepared.
No. Planning permission and Building Regulations approval are separate from the Party Wall etc. Act 1996. A project may need to comply with all of them.
Richard Hourican. Specialist Party Wall surveyor, London

Richard Hourican, Company Director

BSc (Hons). HND Build. MCIOB. C.Build E MCABE. ARICS. MFPWS. MPTS

As a specialist Party Wall surveyor, Richard Hourican will protect your interests during building works.

Are you planning a building project – perhaps an extension, loft conversion or basement – that is on or adjacent to your property’s boundary line? Or has a ‘Party Wall’ notice dropped on the doormat informing you of a neighbour’s impending works?

It’s essential to understand all the implications of building plans. If you don’t, it could cost thousands. Our job is to ensure everything is done correctly – and that it doesn’t!

Contact us


Follow us:

90 Google Reviews for London Party Wall Surveyor
Google logo
Charlie
Charlie
01 Aug 2025

I found out I needed party wall awards from no less than 8 neighbours and AFTER strip out works. Richard Hourican made saving the day a breeze, meeting all our new neighbours and walking them through the somewhat complicated party wall process. I had been told that one could do party wall awards yourself, I now understand there is absolutely no way that would have been done correctly or as efficiently without the help of Richard and his team. I recommend you call him and explain your situation, he'll sort it and give you a very reasonable fee for the pleasure.

Martin Azzinnaro
Martin Azzinnaro
26 Jul 2025

I can’t recommend Richard and Hourican Associates highly enough. From the outset of our loft conversion project, they demonstrated professionalism, deep expertise, and a calm, solution-focused approach that proved invaluable. Not only did Richard provide clear, practical guidance through the technical and regulatory aspects, but he also managed sensitive party wall matters with diplomacy and clarity. His ability to communicate effectively, mediate concerns, and ensure we remained compliant with all building approvals gave us great peace of mind throughout the process. If you're considering any home extension or loft work, especially where neighbour relations or party wall matters might become tricky, I’d strongly recommend working with Hourican Associates. An absolute asset to any project.

James Williamson
James Williamson
11 Jul 2025

Provided excellent advice on handling of a party wall award - would recommend.

Roberto Palmer
Roberto Palmer
24 Jun 2025

Very professional service

N. Burgess
N. Burgess
28 Apr 2025

Richard came highly recommended and I wouldn't hesitate to recommend him to anyone - especially if, like us, the party wall issues are complex. Richard is terrifically knowledgeable about the practices and law concerning party wall boundaries and very experienced. He is also great to deal with - responsive and highly professional. In our case, he was able to navigate the complexities (and personalities involved) with great skill. We are enormously grateful to him.

Peter Stimson
Peter Stimson
06 Mar 2025

Richard has acted as my Party wall surveyor and has has been incredibly responsive, knowledgeable and helpful throughout the process - he has a great set of contacts so if he doesn’t know the answer to something, he’ll know a man you does - throughly recommend

Gang Hu
Gang Hu
26 Feb 2025

Our friend introduced Richard to us to help on party wall matters. His work was delivered in a very efficient and timely way with high quality. Great experience and highly recommended.

Ash Island Lofts
Ash Island Lofts
20 Feb 2025

I first met Richard in Sept 2016 for a coffee, he went through his services and we gave him a trial run on a fairly complex party wall award requirement for a mid terrace in Fulham SW6. He booked the Schedule of Condition survey the following day and had the awards in my email within the week. Richard is now our main recommended PWS and since then has completed 100s of jobs for our clients. Richard is courteous, strong on customer service, good value, extremely knowledgeable and always a pleasure to deal with.

Jack
Jack
18 Feb 2025

I have worked with Richard for few years now and have nothing but praise. Fast acting, fair costing and thorough work. Clear communication is given throughout which makes working with Richard so much easier.

D Wilks
D Wilks
13 Jan 2025

I have worked with Richard on various basement projects in London and always found him very quick to respond to any emails and gets the party wall awards in place quickly with a fixed costs. He is our go to Party Wall surveyor..

CH Chiam
CH Chiam
18 Dec 2024

This is the second time I’ve used their party wall services. I find Richard to be very knowledgeable and always has time to answer my questions. I’ll recommend his services to my friends.

Cameron Brown
Cameron Brown
17 Nov 2024

Hourican Associates Ltd came recommended and quote was fair. Managed complex party wall situation with 5 neighbours for a loft extension. Schedule of conditions conducted and party wall agreements issued efficiently. Responsive when questions/issues arose.

Contact us for advice on how the Party Wall Act applies to your project & get a free quotation.

Contact us