Start the Party Wall process before your programme depends on it
If your proposed works fall within the Party Wall etc. Act 1996, you must serve the appropriate notice on each relevant Adjoining Owner before exercising the statutory rights.
Before a dispute arises, Hourican Associates can advise on the proposals, identify the relevant owners and serve notices on your behalf with written authority. If a dispute later arises and a surveyor is appointed under section 10, the appointed surveyor's statutory role is to resolve that dispute fairly rather than act as an advocate.
Early review is particularly useful where drawings are still being developed, because notice periods, ownership checks and neighbour responses can affect when notifiable works are able to begin.
Building Owner checklist
- Establish whether the proposed works fall within the Act.
- Identify every relevant Adjoining Owner.
- Serve the correct notice with the required information and drawings.
- Allow the statutory notice period unless earlier written agreement is obtained.
- Resolve any statutory dispute before exercising the relevant rights.
Which Party Wall procedure might apply?
The construction details determine whether notice is required. A single project can involve more than one part of the Act.
New wall at the line of junction
Section 1 can apply where you propose a new wall at or astride the boundary between properties.
Notice period: normally at least 1 month.
Boundary and line-of-junction guidanceWork to a party wall or party structure
This can include cutting into, raising, underpinning or otherwise carrying out work to an existing party wall or party structure.
Notice period: normally at least 2 months.
Party structure guidanceQualifying excavation near neighbouring foundations
Section 6 may apply to excavation within 3 metres or, in some cases, 6 metres where the proposed depth satisfies the statutory foundation tests.
Notice period: normally at least 1 month.
Excavation Party Wall guidanceNotices normally remain effective for 12 months. Planning permission or Building Regulations approval does not replace the separate requirements of the Party Wall etc. Act 1996.
How our Building Owner service works
We keep the statutory process separate from the wider design and planning process so the Party Wall requirements are dealt with at the right stage.
Review
Send us the address, drawings and structural information. We identify the parts of the proposals that may be notifiable.
Owners & notices
We help identify the relevant Adjoining Owners and prepare and serve the appropriate notices with supporting information where required.
Neighbour response
Written consent may allow the statutory dispute procedure to be avoided. If a dispute arises, the surveyor appointment process begins.
Survey & Award
Where appropriate, a Schedule of Condition is prepared and the appointed surveyor or surveyors settle the matters in dispute by Party Wall Award.
Works proceed
The notifiable works proceed in accordance with the Act and, where one has been made, the Award. Further statutory issues can be addressed if they arise.
No statutory dispute at that stage
If the Adjoining Owner gives valid written consent, a Party Wall Award may not be required. Your obligations under the Act still continue, including avoiding unnecessary inconvenience and making good qualifying damage.
Building Owner guidanceAgreed Surveyor
If a dispute has arisen and both owners concur in appointing the same surveyor, one Agreed Surveyor can settle the matters in dispute impartially.
Agreed Surveyor roleTwo-surveyor procedure
Each owner appoints a surveyor. Those surveyors select a Third Surveyor and work to resolve the statutory dispute and agree the Award.
Adjoining Owner Surveyor servicesFor section 2 and section 6 notices, no written response within 14 days normally means a dispute is deemed to have arisen. Section 1 line-of-junction notices operate differently, so the consequences of non-response depend on the notice type.
Building Owner Party Wall fees
We provide the proposed scope and fee before instruction. More complex, multi-owner and basement matters are quoted individually.
Party Wall Notice
from £150 + VAT per Adjoining Owner
Preparation and service of the appropriate Party Wall Notice.
Schedule of Condition
typically £385–£585 + VAT depending on the works and property size
A written and photographic record of relevant visible condition before works.
Full Party Wall service
typically £1,100–£1,500 + VAT depending on project size and complexity
Includes notice, survey and Party Wall Award where required.
Basement surveys are priced separately because they generally require a more detailed inspection of the property and proposals. The Building Owner will also commonly be responsible for the reasonable fees of an appointed Adjoining Owner's Surveyor where the works are solely for the Building Owner's benefit.
What should you send us?
- Your property address.
- Existing and proposed architectural drawings.
- Structural drawings or engineer information where available.
- Excavation depth and foundation information where relevant.
- Your intended works start date.
Common procedural problems
- Serving the wrong notice or omitting required information.
- Missing a relevant freeholder, leaseholder or neighbouring structure.
- Serving notice too late for the intended programme.
- Starting notifiable works before the statutory route allows them to begin.
- Assuming planning or Building Regulations approval replaces Party Wall compliance.
Why appoint Hourican Associates?
A Building Owner service needs both practical construction knowledge and careful administration of the statutory process.
Hourican Associates is a Chartered Building Consultancy specialising in Party Wall surveying across London. The firm is regulated by RICS. Richard Hourican's supplied qualifications and memberships are MFPWS, BSc (Hons), MCIOB, MCABE and AssocRICS. His Pyramus & Thisbe Society membership is company-supplied, pending a current membership record.
We are based at Chiswick Park and advise on residential and commercial Party Wall matters across Greater London, from straightforward alterations to complex excavation and basement projects.
What you can expect
- Clear advice before notices are served.
- Accurate notice preparation using the available project information.
- Professional communication with neighbours and appointed surveyors.
- Practical Awards that address the matters within the surveyors' jurisdiction.
Useful information for Building Owners
These pages cover the documents, appointment routes and common project types that Building Owners most often need.
Building Owner FAQs
These questions cover practical points not already explained above.
Yes. The duty to serve notice rests with the Building Owner, and you may serve it yourself. A surveyor or other agent can also serve a notice on your behalf where properly authorised. The notice still needs to contain the information required by the Act.
No. For the section 10 dispute-resolution procedure, the Act defines a surveyor as a person who is not a party to the matter. A Building Owner therefore cannot appoint themselves as the statutory surveyor.
The Act allows certain counter-notices and enables appointed surveyors to determine matters within their statutory jurisdiction. It does not give an Adjoining Owner a general veto over lawful development, but the way notifiable works are carried out can be regulated to address relevant rights and safeguards.
Only where the statutory route allows it and the required written agreement has been obtained. Otherwise the relevant one- or two-month notice period must be observed before exercising the statutory right.
An Adjoining Owner can serve a counter-notice in circumstances provided for by the Act. If you receive one, it should be reviewed promptly: the Building Owner normally has 14 days to respond before a dispute is deemed to have arisen.
The Act does not contain its own enforcement procedure for failure to serve notice, but an Adjoining Owner may seek a court injunction to stop the work or pursue other civil remedies. If work has already started, project-specific professional and potentially legal advice should be obtained promptly.