Adjoining Owner Party Wall Surveyor in London
If your neighbour is carrying out notifiable works, the Party Wall etc. Act 1996 gives you rights and protections. We review the notice and proposals, explain your options and, where appointed under the Act, help resolve the matters in dispute impartially.
Received a Party Wall Notice from your neighbour?
Before responding, it is sensible to understand what work is proposed, whether the notice is appropriate and what practical safeguards may be needed for your property.
If a dispute arises, you can appoint your own surveyor or concur with the Building Owner in appointing one Agreed Surveyor. A surveyor appointed under section 10 is not a personal advocate: the statutory role is to resolve the matters in dispute fairly and impartially under the Act.
Hourican Associates acts for Adjoining Owners across London on loft conversions, extensions, chimney alterations, structural works, excavations and basement projects.
Your rights under the Act
- Appoint a surveyor to resolve a statutory dispute.
- Require reasonably necessary measures to protect your property from foreseeable damage.
- Not be caused unnecessary inconvenience by the notifiable works.
- Be compensated for qualifying loss or damage caused by relevant works.
- Ask for security for expenses where the statutory circumstances justify it.
What can you do after receiving a notice?
The correct response depends on the type of notice, the proposed works and whether you are satisfied with the information and safeguards provided.
Consent in writing
If you understand the proposed works and are comfortable proceeding without the statutory dispute procedure, you may be able to consent in writing.
Consent does not remove the Building Owner's responsibilities for damage caused by the notifiable works. Different rules apply to some section 1 boundary-wall notices.
Use one Agreed Surveyor
Where a dispute has arisen and both owners concur, one impartial surveyor can be appointed to settle the matters in dispute and make the Award.
How the Agreed Surveyor role worksAppoint your own surveyor
You may appoint an Adjoining Owner's Surveyor and the Building Owner appoints a separate surveyor. The two appointed surveyors select a Third Surveyor and work to resolve the dispute under the Act.
Although separately appointed, both surveyors must act consistently with the Act and work toward a fair and impartial Award.
For section 2 Party Structure Notices and section 6 excavation notices, failing to respond within 14 days means a dispute is deemed to have arisen. Section 1 notices concerning new walls at the line of junction operate differently, so the notice type matters.
How an Adjoining Owner appointment works
The scope varies by project, but most separate-surveyor appointments follow the same broad stages.
Review the notice
We review the notice, drawings and proposed works and identify the matters requiring consideration under the Act.
Formal appointment
You appoint your surveyor in writing. The Building Owner's Surveyor and Adjoining Owner's Surveyor then select a Third Surveyor.
Technical review
The surveyors consider drawings, construction details, access, protection and other matters relevant to the statutory dispute.
Condition & Award
A Schedule of Condition may be prepared and the surveyors agree the Party Wall Award setting out how the notifiable works may proceed.
During the works
If a matter within the surveyors' jurisdiction arises during construction, it can be inspected and dealt with under the Act where appropriate.
Schedule of Condition
A Schedule of Condition is not compulsory under the Act, but it is commonly prepared because it records the visible condition of relevant parts of the Adjoining Owner's property before the works start.
Written notes and photographs provide a reference point if questions about damage arise later.
Schedule of Condition SurveysDamage and making good
The Building Owner is responsible under the Act for putting right damage caused by the exercise of the statutory rights. Where damage is disputed, the pre-works record and other evidence can help determine what happened.
Where the Building Owner is required to make good damage, the Adjoining Owner can require the expenses of making good to be determined under the Act and paid instead of the Building Owner carrying out the repair.
Party Wall dispute resolutionWho pays the Adjoining Owner's Surveyor?
Where the notified works are solely for the Building Owner's benefit, the Building Owner will usually pay the reasonable costs associated with drawing up the Award, including the Adjoining Owner's Surveyor's reasonable fees.
The Act does not set fixed surveyor charges. Different cost-sharing rules can apply where works are required because of repair, defect or shared benefit.
We confirm the appointment basis and fee arrangements clearly before progressing the matter.
Usually paid by the Building Owner
Subject to the circumstances of the works and the surveyors' determination under the Act.
Why appoint Hourican Associates?
Adjoining Owner appointments require a clear understanding of construction, the Party Wall etc. Act 1996 and the limits of the surveyor's statutory role.
Hourican Associates is a Chartered Building Consultancy specialising in Party Wall surveying across London. The firm is regulated by RICS. Richard Hourican's supplied qualifications and memberships are MFPWS, BSc (Hons), MCIOB, MCABE and AssocRICS. His Pyramus & Thisbe Society membership is company-supplied, pending a current membership record.
We are based at Chiswick Park and work across Greater London on residential, commercial and complex neighbour matters.
What you can expect
- Clear explanation of the notice, proposed works and statutory options.
- Practical review of construction details and foreseeable property risks.
- Professional communication with the Building Owner's Surveyor.
- Impartial administration of the Act rather than adversarial representation.
Useful Party Wall information for Adjoining Owners
These pages explain the documents, appointment routes and statutory procedures most relevant after receiving a Party Wall Notice.
Adjoining Owner FAQs
These answers cover common issues not already explained above.
No. You do not need a professional adviser merely to respond to a notice. You can reply yourself. A surveyor appointment becomes relevant where a statutory dispute has arisen and needs to be resolved under section 10.
Potentially, but only if both owners are comfortable concurring in that person's appointment as the Agreed Surveyor. If you do not wish to agree to that appointment, you may appoint a separate surveyor where a dispute has arisen.
The Act allows an Adjoining Owner to request security for expenses in appropriate circumstances. Whether security is justified, and the amount, depends on the proposed works and the risk the statutory right is intended to address.
The Act is intended to facilitate lawful development while protecting neighbouring owners. A surveyor does not have a general power to stop properly authorised works. If notifiable works start without the required notice, an Adjoining Owner may need legal advice about possible court remedies.
Yes. Either owner may appeal an Award to the County Court within 14 days of service. An appeal can involve legal and cost consequences, so independent legal advice may be appropriate before taking that step.
The Act does not contain its own enforcement procedure for failure to serve notice. Where notifiable work has started without the required notice, an Adjoining Owner may seek legal remedies, including potentially an injunction. This is a civil-law issue and legal advice may be needed.